Cleaner air and a greener future: Think Hire’s solutions for Carnell’s EcoSite

Carnell EcoSite Case Study

Overview

Cleaner air and a greener future: Think Hire’s solutions for Carnell’s EcoSite.

In partnership with Carnell as part of their EcoSite initiative, we successfully deployed Solartainer Versatile, Sitegrid X45 hybrid battery, and Solar Skyframe units across several key highway compound setups in 2023, including high-profile sites like the M69 Ansty and M1 J28 Pinxton Interchange.

The Think Energy Panorama remote monitoring system supported all setups and provided live data on energy usage, fuel consumption, and emissions. By replacing traditional diesel generators with our off-grid, renewable energy units, we helped Carnell dramatically reduce their carbon footprint, nitrogen oxides (NOx), and particulate matter emissions.

The Results

Across all key sites, we achieved impressive reductions in both carbon emissions and harmful pollutants, along with significant operational cost savings. The project’s key statistics are as follows:

CO2 Saved 169 Tonnes CO2e Saved
Fuel Saved 65,815 Litres Fuel Saved (63% Reduction)
Total Savings £60,923 Overall Project Savings
NOx Reduction 61% NOx Emissions Cut

Award-Winning Impact

This remarkable project didn’t go unnoticed. Carnell’s EcoSite initiative was selected as a winner at the International Green Apple Environment Awards 2024.

Better Air Quality, Healthier Worksites

These emission reductions directly impact the health of workers and nearby communities. By significantly cutting particulate matter (reduced by 63%) and NOx emissions, Carnell’s EcoSite solutions are not only protecting the environment but also enhancing the health and safety of workers who spend long hours near generators.

A Commitment to Collaboration

Our journey towards decarbonisation is strengthened by our collaborative approach. Through partnerships like the Midlands Collaborative Community’s Net Zero Working Group, we share best practices. Following Think Hire’s demonstration at the A38 Fradley compound, delivery partners such as Chevron have implemented similar solutions, achieving significant CO2 savings on their own projects.

Related Case Studies

Ashe Group Saves £8,103 & Cuts 22 Tonnes of CO2 with Solar Power

Ashe Group

Summary

At the Journeys Academy development in Potters Bar—a new build school for children with special educational needs—Ashe Group faced a delay in grid connection... Read more
Read Case Study
Bouygues E&S Solutions Ltd: Cut Site Costs by 47% & CO2 by 17 Tonnes

Bouygues E&S Solutions Ltd

Summary

The client sought to identify a more sustainable, environmentally sympathetic and cost-effective solution to off-grid power on their sites... Read more
Read Case Study
G&V Gallagher Ltd: How They Slashed Site Costs by 64% & CO2 by 18 Tonnes

G&V Gallagher Ltd

Summary

The client sought to identify a more sustainable, environmentally sympathetic and cost-effective solution to off-grid power on their sites. The key requirement was to reduce their carbon output on-site and the number of pollutants produced as a by-product of their activities... Read more
Read Case Study
George Leslie Achieves 100% Renewable Power for Innovation Day

George Leslie

Summary

When George Leslie set out to host their Innovation Day, they wanted the event to reflect their sustainability ambitions, powered entirely by clean energy. Traditionally, temporary events rely on diesel generators, but George Leslie chose a different path by partnering with Think Hire.
Read Case Study
Cora Homes: How They Cut Site Costs by 58% & CO2 by 127 Tonnes

Cora Homes

Summary

The main requirements of this project were to minimise their impact on the environment and significantly reduce their carbon footprint without impacting site efficiency. Our solution? A Solartainer L to provide power to cabins on the site to reduce cost and environmental impact.
Read Case Study
How Miller Homes Ltd Cut Onsite Fuel Consumption by 96% with Solar

Miller Homes Ltd

Summary

The main requirements of this project were to reduce the client's carbon output onsite and to lower the number of harmful pollutants produced as a by-product of their work. Our solution was a three-phase Solartainer L to provide power to cabins onsite.
Read Case Study